Skip to content

Jobsite and Mobile Plant

Using Mobile Crushers for Construction and Demolition Waste (Concrete Recycling)

Using Mobile Crushers for Construction and Demolition Waste (Concrete Recycling)

Whether mobile crushing of demolition waste pays off depends on on-site versus central processing, separating piles through selective demolition and where the product will be used. A crusher bucket suits small jobs, a portable impactor with by-pass screen suits medium volume, and a mobile crushing and screening plant suits continuous work needing saleable fractions.

The Ideal Mobile Crushing Plant Configuration for Road Construction and Sub-Asphalt Material

The Ideal Mobile Crushing Plant Configuration for Road Construction and Sub-Asphalt Material

A mobile crushing plant for road work is configured backwards from the specified layer: jaw-cone, jaw-impact or primary impact stages by rock type, screen decks that set the number of fractions, and relocation along the route. Crushing capacity is balanced against the mobile plant-mix unit through stockpiles; grading acceptance depends on the project specification and sieve tests.

Choosing a Mobile Crusher for River-Bed Aggregate Production

Choosing a Mobile Crusher for River-Bed Aggregate Production

For river material, machine choice starts not with tonnage but with whether the material needs crushing, washing or only screening. Sample tests point to the right setup among the ME1650, YM1240/YM1650, Mobil 90 and GNR-MVSI 900.

Mobile Screening Plant or a Crushing and Screening Combination?

Mobile Screening Plant or a Crushing and Screening Combination?

If most of your material is already below 100 mm and clean, a mobile screening plant without a crusher (GNR ME1650, ME2060) is enough; blasted quarry rock or deposits with a high share of oversize need a crushing and screening combination. The decision is driven by feed size, oversize share and rock abrasiveness rather than by hourly capacity.

Tracked Mobile Crusher or Towable Semi-Mobile Crusher?

Tracked Mobile Crusher or Towable Semi-Mobile Crusher?

A tracked crusher suits work that relocates often within a site on difficult ground, while a towable semi-mobile plant suits work that moves between distant job sites and stays long at each. Relocation count, crushing circuit scope and ground decide the choice before crusher type does.

Urban jobsite mobile crusher operating plan

Urban jobsite mobile crusher operating plan

On an inner-city site the limit is rarely crushing capacity. Manoeuvring room, the permitted working window and the neighbour relationship set the pace, and the plan has to be built around those three.

Jobsite material flow and stockpile layout

Jobsite material flow and stockpile layout

Conical stockpile volume follows from the angle of repose and the base radius; a ten metre radius cone holds roughly twelve hundred tonnes, which on most sites equals only one to three days of output.

Using Mobile Crushers for Recycling and Asphalt/Concrete Crushing

Using Mobile Crushers for Recycling and Asphalt/Concrete Crushing

Demolition concrete, asphalt slabs and millings are different feeds; tracked impact crushers turn them into cubical aggregate in one stage. The real gains come from removing steel at the right point, pre-screening and avoiding over-crushing asphalt.

How to Choose a Mobile Crusher for 100-300 Tonnes per Hour

How to Choose a Mobile Crusher for 100-300 Tonnes per Hour

The right mobile crusher step comes from dividing the daily target by net operating hours and adding closed-circuit recirculation; the resulting load should sit mid-range in the catalogue band. Candidate models for 100, 150, 200, 250 and 300 t/h are compared by feed size, screen area and generator kVA.

A Guide to Mobile Screening Plants for Contractors Moving from Site to Site

A Guide to Mobile Screening Plants for Contractors Moving from Site to Site

For a contractor who relocates often, choosing a mobile screening plant starts with the material: GNR ME1650 or ME2060 for clean, dry sand and gravel, YM1240 or YM1650 for clayey and wet material. All four take a 0-100 mm feed, and transport size, water and power preparation and deck planning decide output on every new site.

Rent or buy a crusher for a short-term project?

Rent or buy a crusher for a short-term project?

One number settles this: utilisation, meaning how many of the available working days the machine will genuinely run. Below the threshold, ownership fixed costs spread across too few hours and the cost per tonne climbs. This article builds the break-even from project duration and tonnage.

Mobile Plant Transport and Permit Planning

Mobile Plant Transport and Permit Planning

The number of frames sets the number of trucks, and the number of trucks sets the size of the permit file. Exceed width, height, length or axle load by any margin and the load becomes an abnormal one. The route survey belongs before loading, never after.

Road sub-base and base course aggregate specification

Road sub-base and base course aggregate specification

Sub-base and base course are not the same product from a different pile. Grading, cleanliness and strength expectations separate them, and this guide maps each criterion onto what the plant must actually produce.

Plant Mix Road Base Gradation Compliance

Plant Mix Road Base Gradation Compliance

Plant mix base material is rejected far more often for uncontrolled blend ratios and moisture than for anything the machinery did. This article walks through the test methods behind the sieve curve, where deviation from the approved mix formula is caught, and which three records a shift must keep before compaction begins.

Rebar Separation When Crushing Reinforced Concrete

Rebar Separation When Crushing Reinforced Concrete

Steel embedded in demolition concrete is the single most expensive contaminant a recycling line handles: it wraps the rotor, wedges the chamber and breaks wear parts. This article sets out where the steel is taken out, with which equipment, and in what order, so the machine is protected and the scrap becomes revenue.

On-site concrete demolition crushing workflow

On-site concrete demolition crushing workflow

Demolition concrete processed where it falls avoids paying twice: once to haul it away and once to buy fill. A workflow that pins pre-sorting, feeding, crushing, screening and stockpiling to shift hours turns a rubble pile into measured tonnes by close of day.

Site Ground Preparation for Mobile Crusher

Site Ground Preparation for Mobile Crusher

A tracked or wheeled crushing plant does not need a reinforced concrete foundation, but it does need a platform that will not settle, will not hold water and has measurable stiffness. This article groups the work into three testable headings: bearing capacity verified by plate load testing, levelling within the machine's own slope tolerance, and drainage that moves water off the pad.

Mobile crushing plant site commissioning plan

Mobile crushing plant site commissioning plan

From the moment the unit is unloaded to the first tonne produced there is a fixed order: ground acceptance, set-down, levelling, unfolding, no-load running, first feed. Each step here carries its own acceptance criterion.

MGPJ 110 Primary Jaw and GNR 03 Mobile Plant Now Running Side by Side

MGPJ 110 Primary Jaw and GNR 03 Mobile Plant Now Running Side by Side

A line combining a semi-mobile jaw crusher with an impact crushing and screening plant has been commissioned, raising both capacity and fines output.

60 m³/h Diamond 60 Mobile Concrete Plant on Its Way to Bulgaria

60 m³/h Diamond 60 Mobile Concrete Plant on Its Way to Bulgaria

The 2025 model Diamond 60, the smallest plant in our mobile concrete batching family, has been dispatched to our customer in Bulgaria.

What Does a Mechanical Stabilization Plant Do? Stationary and Mobile Models, Capacities

What Does a Mechanical Stabilization Plant Do? Stationary and Mobile Models, Capacities

A mechanical stabilization plant prepares the stabilized mix used in the sub-base layers of roads and airport runways. It combines a control cabin, a feed hopper and a mixer, and we build it in stationary (400-500 t/h) and mobile (300-400 t/h) versions to suit each project's needs.

Concrete Batching Plant Guide: Equipment, Fixed and Mobile Types, Mixer Options

Concrete Batching Plant Guide: Equipment, Fixed and Mobile Types, Mixer Options

A concrete batching plant mixes aggregate, water and cement in set proportions to make ready-mix concrete and fills truck mixers; it combines a silo, a mixer, a feed belt and an aggregate hopper and can be fixed or mobile.

3-Chassis Mobile Crushing and Screening Plant Exported to Malta

3-Chassis Mobile Crushing and Screening Plant Exported to Malta

We shipped another new mobile crushing and screening plant consisting of 3 chassis to Malta.

2024 Model GM M-100 Mobile Concrete Silo on Its Way to the UK

2024 Model GM M-100 Mobile Concrete Silo on Its Way to the UK

We have completed the export of our newly developed GM M-100 mobile concrete silo to a customer in the United Kingdom.

Crushing on the jobsite: making aggregate where it is used

When a construction site buys every tonne of aggregate from a distant quarry, most of the money is spent on wheels rather than on stone. A mobile crushing and screening plant reverses that arithmetic. Rock from excavation, concrete from demolition and off-spec material along a road alignment are processed inside the site boundary and turned back into a usable product. This section of the knowledge centre covers the engineering behind that idea: ground preparation, commissioning, recycling circuits, road base and plant-mix production, transport dimensions and permits, and the discipline of setting up a plant that will be dismantled again in a few months.

The difference between a jobsite plant and a quarry plant is time. In a quarry the plant stands in one place for a decade. On a construction site the same machine is erected, produces for one season and is loaded back onto a trailer. That is why a site engineer cannot judge a plant on cost per tonne alone: set-up time, mobility, permitting load and how easily the ground can be handed back all belong in the same evaluation.

The ground under the plant is the real foundation

A mobile plant needs no concrete foundation, but it certainly needs ground. Machine weight combined with the dynamic forces produced by a crusher is more than enough to consolidate loose fill. Fresh fill, soft topsoil and a pad without drainage are the three classic mistakes; a plant that looks perfectly aligned during the first shift loses its level within days, and screen feed goes with it.

Preparing the pad

The working area must be levelled and compacted. Compacted crushed stone, firm undisturbed soil or an existing concrete apron are the preferred surfaces. Where bearing capacity is uncertain, a field measurement such as a plate load test settles the question; guessing means re-excavating under a running plant later. On marginal ground, steel plates, hardwood cribbing or engineered support pads spread the load over a larger contact area.

Stabilising and levelling

Legs and supports are fully extended so the load travels from the chassis into the ground. Levelling is verified with an instrument on the feeder and screen bodies, not by eye. A screen sitting out of level pushes material to one side and wears a single band of the screen media. Where the plant has to be raised for conveyor clearance, the weight is never left standing on hydraulic cylinders; it is blocked and seated on locking pins.

The commissioning sequence

Commissioning happens in three stages. The cold stage checks electrical, hydraulic and mechanical connections, fastener torque and fluid levels, then runs the plant unloaded so motors, drives and switchgear can be observed without material. The second stage is a loaded trial with real feed: vibration, noise and bearing temperatures are monitored while feed rate and crusher setting are calibrated to the target product. The third stage is continuous running that proves product consistency and mechanical stability. Sites that skip this order spend their first week collecting breakdowns instead of tonnes.

Selecting a mobile plant by feed size

The first number that decides plant selection on a jobsite is not the target tonnage but the size of the largest lump. If blocks from the excavation exceed the feed opening, rated capacity stays on paper: the crusher bridges, and the excavator operator spends the shift sorting oversize. The table below compares feed and capacity figures for General Makina mobile crushing plants across different site scales.

PlantMaximum feed sizeCapacityOutput size settingOptional generator
General 640500 mm40-70 t/h0-100 mm300 kVA
General 01700 mm120-180 t/h0-100 mm550 kVA
GNR-MC110900 mm200-300 t/h0-100 mm750 kVA
General 021000 mm180-250 t/h0-100 mm660 kVA

All four plants are configured to deliver standard fractions such as 0-5, 5-12, 12-19 and 19-40 mm, and those cut points can be changed through screen media selection to match a project specification. On a contained infrastructure package the General 01 mobile crushing plant covers shift demand comfortably, while a long road project that walks along its alignment benefits from the larger feed opening of the General 02 mobile crushing plant, which removes the need for a separate pre-crushing step. On demolition sites where the machine moves between piles every few days, the GM-90JP tracked jaw crusher positions itself without a tractor unit. Before committing to a size and a chassis type, compare the full mobile crushing plant range and read it alongside the mobile, tracked and stationary plant selection guide.

Recycling demolition concrete and excavated rock

The economics of on-site recycling come from two lines in the budget: spoil that never leaves and aggregate that never arrives. Crushed concrete has an angular particle shape and a rough surface texture, so it interlocks well and forms a stable layer once compacted. That makes it a genuine alternative to natural aggregate for fill, sub-base and internal haul roads.

Removing contaminants

The decisive process is not crushing but cleaning. Timber, plastic, insulation and soil make the product unusable, and reinforcing steel damages both the material and the belts. A recycling circuit therefore combines magnetic separation, air separation and, where the input is variable, a manual picking station. The concrete recycling plant guide is a detailed starting point for the whole circuit.

Grading and moisture

A sub-base material aims at continuous grading: smaller particles fill the voids between larger ones so that compaction produces a dense, load-bearing layer. Maximum particle size follows layer thickness. The fines content is not left to chance, because excess fines impair drainage and make the layer unstable when wet. Recycled aggregate is more absorbent than natural rock, so slightly more water is usually needed to reach optimum moisture during compaction. Acceptance criteria always belong to the road authority of the country in question; bearing and abrasion limits are read at the start of the project, and production is set up to meet them rather than argued about afterwards.

Road base and plant-mix production

Road work needs more than crushing and screening. Material has to be blended, stabilised with a binder where the design calls for it, moistened and laid. A plant-mix circuit combines screened fractions in defined proportions to produce a homogeneous base material. On long alignments a mobile plant-mix and stabilisation unit moves forward with the works while blend ratio, water and binder dosage are logged shift by shift. For layer build-up and plant layout, follow the road base plant-mix facility guide. Where the same site also pours concrete, feeding a mobile concrete batching plant from the aggregate circuit removes another haulage line.

Transport, permits and site layout

Road transport is the most underestimated item in a mobile plant project. Transport height, width and axle loads are calculated in advance against every bridge and underpass on the route, and the need for abnormal load permits, escort vehicles or night movement follows from that calculation. The turning radius of the site entrance matters just as much: a trailer that cannot swing in leaves the plant waiting at the gate.

The permit file

Permitting concerns the activity rather than the machine. Temporary plant installation, dust and noise, waste acceptance, water use and plant traffic are each assessed separately. Sites processing demolition waste also document what arrived and where the product went. If the file is not closed before mobilisation, the plant stands idle on hire and site overheads.

Layout

Layout follows material flow: feed stockpile, plant, product stockpiles and loading bay arranged as a one-way cycle. Throwing products to sufficient height with a conveyor belt shortens loader cycles and keeps stockpiles from merging. Prevailing wind decides where crusher and screen discharge points sit, so that the dust source is not placed on the same line as the site office or neighbouring buildings.

Balancing set-up, production and demobilisation on short projects

If erection takes a week and dismantling three days on a three-month contract, that time comes straight out of the production calendar. On short jobs the right plant is therefore not the largest one but the one that starts producing fastest with the least infrastructure. Where no grid connection exists, generator operation is planned from the outset, and the generator ratings in the table above also drive fuel consumption and storage volume. A wear-part stock stays on site: waiting for a screen mesh or a wear plate at a remote location is the most expensive way to lose a shift.

At the end of the project the site is cleared as deliberately as it was built. Stockpile areas are stripped, fines are not left to blow, temporary roads are removed and the ground is reinstated to the contract condition. The plant is returned to transport configuration, wear parts are inspected, and shortages are made good before the next site rather than during its first shift. Teams that want the decision in numbers can build set-up, transport and production items into one sheet with the operating cost calculator. Tell us the excavation material, the fractions your specification demands and the duration of the contract, and our engineers will work out the plant configuration and the layout for that particular site with you.

Frequently Asked Questions

Does a mobile crushing plant need a concrete foundation?

No. Mobile plants are designed to work without a permanent foundation, but they still need a levelled and compacted pad. Fresh fill or undrained ground settles under machine weight and crusher vibration, and the plant loses its level within days.

Which figure decides plant size on a construction site?

The largest lump in the feed, not the target tonnage. Maximum feed size is 500 mm on the General 640, 700 mm on the General 01, 900 mm on the GNR-MC110 and 1000 mm on the General 02; capacity only becomes meaningful once the feed opening is respected.

Can crushed demolition concrete replace natural aggregate?

For fill, sub-base and internal haul roads it can. Crushed concrete is angular and rough textured, so it interlocks and compacts well. It must be cleaned of timber, plastic and reinforcing steel, and graded to the specification of the relevant road authority.

How should commissioning be sequenced?

Cold checks and a no-load run come first, then a loaded trial on real feed while vibration, noise and bearing temperatures are watched, and finally continuous running to prove product consistency. Feed rate and crusher setting are calibrated during the loaded stage.

What if the site has no mains power?

Generator operation is planned from the start. Optional generator ratings are 300 kVA for the General 640, 550 kVA for the General 01, 660 kVA for the General 02 and 750 kVA for the GNR-MC110, and those ratings drive fuel consumption and on-site storage volume.

When does permitting work have to start?

Well before mobilisation. Temporary installation, dust and noise, waste acceptance, water use and site traffic are separate assessments, and abnormal load transport is checked against every structure on the route. An open file means the plant stands still while hire costs run.