Skip to content

Investment and Cost

Rent or Buy? Mobile Crusher Cost Comparison for Construction Sites

Rent or Buy? Mobile Crusher Cost Comparison for Construction Sites

Renting a mobile crusher looks easy for a short one-off job, but as crushing months per year grow, rent quickly overtakes the cost of ownership. General Makina does not rent machines; for a contractor with continuous work the right choice is to buy a new machine, and a used one does not change that calculation.

100 TPH Mobile Crushing Plant Price and Investment Payback (ROI) Period

100 TPH Mobile Crushing Plant Price and Investment Payback (ROI) Period

A 100 t/h target lands at different points on the General 640, General 800 and GM 100, and the quotation is shaped by crusher layout, undercarriage, screen, generator and delivery scope. Payback equals total investment divided by annual net cash flow and depends most on net crushing hours and contribution per tonne.

Mobile Crushing Plant Hourly Fuel Consumption and Operating Cost Calculation

Mobile Crushing Plant Hourly Fuel Consumption and Operating Cost Calculation

On a mobile crushing plant, hourly fuel consumption is set by the average load drawn from the generator, not its kVA rating, and it can only be measured reliably on site with the top-up method. Once fuel, wear, labour, depreciation and transport are placed in a formula and converted to cost per tonne, holding tonnage turns out to be the deciding factor.

7 Financial Criteria When Buying a Mobile Stone Crushing Plant for Sale

7 Financial Criteria When Buying a Mobile Stone Crushing Plant for Sale

The financial value of a mobile stone crushing plant comes not from its price tag but from cost per tonne, built from capacity fit, wear, energy, transport, product revenue, warranty and growth path. Comparing the seven criteria in one table and buying a correctly sized new plant always pays better than the hidden costs of a used machine.

Mobile Crusher Prices 2026: New vs. Used Plant Cost Guide

Mobile Crusher Prices 2026: New vs. Used Plant Cost Guide

A mobile crusher price is set by scope, not by model name: crusher layout, screen decks, generator and conveyors, so quotations must be compared on equal scope. The low asking price of a used plant melts away with overhaul, downtime and no warranty; on total cost, a new machine is always the right choice.

Annual operating cost budget crushing plant teams can actually use

Annual operating cost budget crushing plant teams can actually use

An operating budget is not one cost per tonne. Energy, wear, lubricants, labour, insurance and lost production each belong on their own line with their own measurement base. This article sets out those lines and shows which monthly deviation signals which problem.

Aggregate Market Demand Analysis

Aggregate Market Demand Analysis

Aggregate is bulky and low in unit value, so geography defines the market. As haul distance grows, freight takes over the delivered price and the sales area shrinks. Demand is forecast fraction by fraction, never as one lump tonnage.

Risks and Advantages to Consider When Buying a Used Mobile Crusher

Risks and Advantages to Consider When Buying a Used Mobile Crusher

A new mobile crusher is always the right choice, thanks to its warranty, wear life starting from zero and a configuration selected for your material. A used plant can only be an unavoidable exception and should never be bought without on-site inspection of rotor, bearings, chassis, screen and panel plus a trial crush.

Concrete Batching Plant Prices: Mobile vs Stationary Plant Cost Comparison

Concrete Batching Plant Prices: Mobile vs Stationary Plant Cost Comparison

The cost gap between mobile and stationary concrete batching plants comes less from the machine price than from foundations, erection and dismantling, transport, silo and aggregate bin scope. The decision should follow how often the plant moves during the project and how much it produces at each location.

Mobile Crushing Plant Prices 2026: 5 Factors That Set the Cost

Mobile Crushing Plant Prices 2026: 5 Factors That Set the Cost

The quoted price of a mobile crushing plant is set by capacity and crusher arrangement, rock hardness and feed size, equipment scope, chassis and installation scope, and how quotations are levelled to the same scope. We explain each factor with data from seven models, General 640 to General 03, and list what to prepare before requesting a quotation.

Used crusher plant investment risk

Used crusher plant investment risk

The cheap part of a used plant is the purchase; the expensive part is five years of parts, downtime and yield difference. This guide turns the decision into countable line items.

Crusher Plant Financing and Leasing

Crusher Plant Financing and Leasing

Buy the same crushing plant for cash, on a loan, under a lease or through a documentary credit and the headline price barely moves, while the cash timing, the balance sheet and the collateral burden behave completely differently. This article compares the four routes and shows which one squeezes an operation and when.

Crushing Plant Feasibility Study

Crushing Plant Feasibility Study

A feasibility study is a decision document, not an equipment list: reserve evidence, market evidence, the technical solution, the financial projection and risk analysis meet in one file. This article sets the order of the sections, the evidence each one demands and the gaps that leave a study weak.

Mobile vs stationary plant ROI comparison

Mobile vs stationary plant ROI comparison

Purchase price on its own settles nothing. Once reserve life, relocations per year and the repeat cost of foundations and erection sit in one present-value table, the gap between a mobile and a stationary plant can change direction within a few years.

Crusher Total Cost of Ownership

Crusher Total Cost of Ownership

Purchase price is a small share of what a crusher will cost you over its life. This article builds the skeleton of a ten-year ownership model: which line items belong in it, which record feeds each one, and which assumptions the cost per tonne is genuinely sensitive to.

Aggregate production cost per ton

Aggregate production cost per ton

Cost per ton is not one figure but the sum of six components. This piece shows what data measures each one, how often it is read, and why the denominator must be saleable tonnage rather than rated capacity.

Crushing plant payback period calculation

Crushing plant payback period calculation

Payback equals total invested capital divided by annual net cash flow; the variable that distorts the result most is not catalogue throughput but the share of the year the plant actually runs.

Crushing and screening plant investment cost: what the budget really contains

Crushing and screening plant investment cost: what the budget really contains

Installed plant cost is far larger than the invoice total of the machines. For plants that handle only solids, a widely used factorial estimate multiplies the delivered cost of major equipment by roughly 3.1 to reach total installed capital. This article opens that multiplier and turns it into line items.

Plant Selection for Basalt Crushing and Screening

Plant Selection for Basalt Crushing and Screening

In this blog post, we explain what basalt is and what is needed to crush and screen basalt.

Tips for Finding a Crusher for Sale

Tips for Finding a Crusher for Sale

Tips for Finding a Crusher for Sale

Jaw Crusher Guide: Feed Openings, Hydraulic Adjustment and the Details Behind the Price

Jaw Crusher Guide: Feed Openings, Hydraulic Adjustment and the Details Behind the Price

Jaw crusher prices depend on feed opening size, primary or secondary type, mobile or stationary design and details such as flywheel, shaft and bearings.

Impact Crusher Manufacturing, Features and Prices

Impact Crusher Manufacturing, Features and Prices

Impact Crusher Manufacturing, Features and Prices

What a Mobile Crusher Offers: Easy Relocation, One Operator and a Single Chassis

What a Mobile Crusher Offers: Easy Relocation, One Operator and a Single Chassis

Built on a single chassis, a mobile crusher moves between sites and lets one operator run all crushing and screening work.

Where Are Modern Stone Crushing Plants Made? Over 50 Years of Manufacturing in Izmir

Where Are Modern Stone Crushing Plants Made? Over 50 Years of Manufacturing in Izmir

Since 1976 we have been manufacturing original-design stone crushing, screening and washing plants in Izmir and standing by our customers with after-sales technical support.

Investment and cost: the numbers that decide the project

No crushing and screening investment is settled by a single machine price. What decides the case is not the amount invested but how many years it takes to come back, at what capacity utilisation, and at what unit cost. So the useful question is never "what does a plant cost" but "what will my cost per ton be, and where does that sit against my selling price". The articles gathered here build the budget line by line, estimate the annual spend, and then test the whole thing against financial criteria.

Everything below is symbolic. You fill the variables from your own quotations and market data: C = total investment, G = annual cash operating spend, T = saleable tons per year, p = average selling price per ton, m = cash cost per ton, K = capacity utilisation, N = economic life, r = discount rate. Absolute prices move with region, currency and power tariffs, so none are quoted here; what is given is the part that does not move — the calculation skeleton.

CAPEX: the one-off investment lines

Equipment set and ancillaries

The equipment set is the most visible part of the budget and, on its own, the least sufficient. A set covers feeder, primary crusher, secondary and tertiary stages, screens, belt conveyors, bins and, where required, a washing group. Two flowsheets delivering the same tonnage can need a different machine count and a very different metre of conveyor, which separates their totals sharply. Narrowing the set through the product selection wizard fixes the technical frame before any budgeting starts. A stationary crushing plant is the starting point for a single long-life site, while the mobile crushing plant family answers relocation-driven work.

Site, foundation and power infrastructure

For a fixed installation, concrete foundations, mounting platforms, retaining and stockpile arrangement, drainage and haul roads form their own heading. On the power side you budget transformer, main panel, cabling and, where the grid is absent, a generator — which lands in CAPEX and then enlarges OPEX through fuel. An automation and control system holds a modest share of this heading yet carries weight far beyond that share in the payback calculation, because it moves both downtime and manning.

Permits, licences and guarantees

Licence fees, environmental assessment, operating permit, guarantees and consultancy make up the most frequently omitted heading. Its real risk is duration rather than amount: any slip in the permit calendar postpones the start of production and shifts the payback year directly. Feasibility work should carry the expected permit duration, not the optimistic one.

Logistics, erection and commissioning

Freight, customs and insurance; crane time and erection labour; electrical connection, no-load and loaded trials and operator training all sit here. A fixed plant pays this once. A configuration that travels between sites regenerates it at every move, turning a capital line into a recurring annual cost. That single distinction is the financial core of the mobile, tracked and fixed plant decision.

OPEX: the annual operating budget

The annual budget is built from six headings: power, wear parts, oil and filters, labour, insurance-tax-overhead, and the production loss caused by unplanned stoppage. Every one of them can be divided by tonnage, and the moment it is divided it becomes comparable. Spare part stocking policy is itself a cost item: a critical part missing on site generates a downtime cost larger than the part. Lead time on crusher spare parts is therefore a financial parameter, not merely a technical one.

Calculation base for each investment and operating line

Line itemTypeCalculation baseMost sensitive to
Equipment setCAPEXMachine and conveyor count in the flowsheetCapacity and number of stages
Foundations and siteCAPEXm³ concrete, m² platformGround bearing capacity, topography
Power infrastructureCAPEXInstalled power (kW), transformer ratingDistance to grid
Permits and guaranteesCAPEXFee schedule plus consultancyApproval calendar
Freight and erectionCAPEX (recurring if mobile)Trips, crane-daysRelocation frequency
PowerOPEXkWh per ton × annual tonsTariff, idle running share
Wear partsOPEXCost per part life in tonsHardness, abrasiveness
Oil, filters, maintenance labourOPEXOperating hoursMaintenance discipline
LabourOPEXShifts × crew sizeAutomation level
Downtime lossOPEXStop hours × hourly contributionSpare part availability
DepreciationNon-cashC / NEconomic life assumption

Building the cost per ton

Cash cost per ton is m = G / T. The trap sits in the denominator: T is not catalogue hourly capacity but realised saleable tonnage for the year. Build it as T = hourly capacity × daily hours × working days × K, where K already contains maintenance stops, feed interruptions, weather and demand swings. When utilisation falls, the fixed-behaving lines — labour, insurance, depreciation — stay the same while being spread over fewer tons, so unit cost climbs. This is the sharpest lever in the whole case. Saleable tonnage is also not produced tonnage: a fraction with no demand sits in stock and pushes its cost onto the fractions that do sell. To test the effect line by line, run scenarios in the operating cost calculator.

How capacity sizing sets investment size

Capacity is the strongest single driver of investment, but the relationship is not linear. As capacity grows, unit cost falls through scale, while tied-up capital and installed power grow. Capacity below demand loses market; capacity far above demand produces low K and a high unit cost. The figures below are real specification data showing how installed power and feed opening grow alongside the capacity step. For a step-by-step comparison see 640-800-950 capacity selection.

ModelMaximum feed sizeCapacityOptional generator
General 640500 mm40-70 t/h300 kVA
General 800600 mm80-120 t/h450 kVA
General 950800 mm120-180 t/h600 kVA

The generator ratings are optional and simply indicate the order of magnitude of installed power; that magnitude is the starting point when you estimate how much of the power bill lands on each ton.

The total cost of ownership window

Total cost of ownership places the purchase price inside lifetime spend: acquisition, operating cost, maintenance and repair, the production loss of downtime and disposal cost are added together, then residual or resale value at end of life is subtracted. On heavy-duty equipment the purchase price is a small part of lifetime cost, which is why a discount won at the quotation stage is easily handed back by a configuration with short wear-part life or poor energy efficiency. Opening the window across the economic life makes the inverse relationship between purchase price and lifetime cost visible. The secondary stage shows this most clearly; the cone versus impact secondary comparison sets out two different wear profiles at the same throughput.

Payback, net present value and internal rate of return

Annual cash contribution is F = T × (p − m). Simple payback is C / F; it ignores the time value of money and belongs at the screening stage only. In discounted payback each year is brought back with F / (1 + r)^t and accumulated until it equals the investment; because discounting shrinks later years, this figure is always longer than simple payback. Net present value is the sum of discounted inflows less the investment, and a positive result means the project creates value. Internal rate of return is the discount rate that drives net present value to zero, expressing the project as an annual percentage return. Use them in order: screen with payback, decide with net present value, compare against alternative uses of capital with internal rate of return. Sensitivity work should flex at least three variables — utilisation, selling price and power tariff.

Financing structures

Buying outright front-loads the cash outflow and lengthens the payback year, but carries no financing charge. Leasing matches payments to the cash the equipment generates and protects working capital; to compare it fairly, discount the lease stream and set it against the outright price. In export transactions, letters of credit and deferred terms tie the delivery calendar to the financial calendar. Whichever structure is chosen, budget the transition period between erection and steady production separately: it produces expense without producing collections.

Sections of a usable feasibility study

A feasibility study that survives scrutiny has six sections: raw material and reserve analysis, product and market analysis, technical solution and flowsheet, investment and operating budget, financial projection with sensitivity, and a risk-and-mitigation table. In the market section, haul radius governs everything, because aggregate price is highly sensitive to transport distance — the market is a geographically bounded one. The application also reshapes the case: a quarry stationary plant suits one long-life site, while recycling and road works sit on shifting ones.

Final check before committing

Before closing the budget, put four things in writing: your capacity utilisation assumption, your demand split by fraction, your wear-part consumption estimate and your permit calendar. Change any of the four and the payback year changes with it; a single number produced before all four are fixed is not a basis for a decision. If you want the line-by-line budget and the capacity scenarios worked through for your own site, send our project team your production target and material data.

Frequently Asked Questions

Which line items make up a crushing plant investment budget?

Five headings: equipment set with ancillaries, site and concrete foundations, power infrastructure, permits and guarantees, and freight with erection and commissioning. The item most often left out sits outside all five — the working capital needed between erection and the first period of steady production.

How do I calculate production cost per ton?

Divide annual cash operating spend by annual saleable tonnage. Take the denominator from realised tonnage corrected by capacity utilisation rather than from catalogue capacity; otherwise unit cost comes out systematically too low.

Which assumption most often breaks a payback calculation?

Capacity utilisation. Leave out maintenance stops, feed interruptions and demand swings and annual tonnage inflates, unit cost looks low and the payback year comes out shorter than it will be. Use the expected case for this variable, not the optimistic one.

Why does total cost of ownership matter more than purchase price?

Because on heavy-duty equipment the purchase price is a small share of lifetime cost. Power, wear parts and downtime loss repeat year after year, so a discount won at quotation is given back over the life of a plant with short part life or weak energy efficiency.

Is a mobile or a stationary configuration more profitable?

Site count and reserve life decide it. On a single long-life site the stationary configuration wins on unit cost because foundations and erection are paid once. Across several sites the mobile configuration can win despite repeated freight and set-up, because it cuts idle time between jobs.

How do I compare leasing against an outright purchase?

Discount the lease payments and compare their present value with the outright price at the same discount rate. Leasing spreads the outflow and protects working capital; buying outright avoids financing charges but front-loads cash and strains the first years of the cash balance.