Skip to content

Mobile crushing plant site commissioning plan

August 19, 2026
Mobile Crushing Plant Site Commissioning Plan, Step by Step

Why commissioning deserves its own plan

A mobile crushing plant site commissioning plan is not about starting the machine. The unit leaves the works mechanically ready; almost all of the time lost on site comes from decisions about ground, access, power and stockpile position that are taken while the plant is already standing there. A commissioning plan pulls those decisions forward and attaches an acceptance criterion to each of them.

The second function of the plan is ownership. If nobody is named for set-down, electrical connection, hydraulic unfolding and first feed, a step is either done twice or skipped entirely. The sequence below exists so that the site crew works from one shared list rather than eight private ones.

Preparation completed before the unit arrives

Ground and layout

The footprint must be compacted, levelled and clear of the low points where water collects. The positions under the hydraulic legs are checked separately, because leg load concentrates on a small area and must never sit on loose fill, a buried service or a freshly backfilled trench. Stockpile areas are marked before the plant lands: the radius the discharge conveyor can reach dictates where the pile grows, and if that direction is chosen badly the conveyor buries itself by the end of the first day.

Power, water and access

Grid supply or generator is decided before mobilisation, because cable size, run length and panel position follow from it. Dust suppression water, a haul route where loaded and empty trucks do not meet head-on, and a maintenance strip left free around the unit all belong on the same sketch.

Set-down, levelling and unfolding order

Once the unit is down, levelling comes first. Conveyors are not unfolded on an out-of-level chassis, because a belt erected on a tilted frame throws material to one side in service and ruins the bed distribution across the screen. Hydraulic legs are extended in opposing pairs and checked on both the long and the short axis. Folding conveyors, walkways, handrails and access ladders follow; nobody steps onto a platform before its handrail is locked in place.

No-load running and the controlled first feed

With electrical and hydraulic circuits complete, the plant is run empty. The point of no-load running is to see noise, vibration, belt tracking and oil weeping while there is no material in the machine, when the cost of correcting a fault is zero. Belts are started individually and watched, then the sequenced start from feeder to crusher is tested. The first feed is deliberately thin and single-source: crusher current, flow over the screen and product size are read together, and no setting is touched until all three have been read.

Commissioning schedule

StepTaskAcceptance criterionRecord kept by
1Ground and layout acceptanceCompacted, drained footprint; leg positions markedSite supervisor
2Set-down on hydraulic legsLevel confirmed on long and short axisErection operator
3UnfoldingConveyors, platforms, handrails and ladders lockedErection operator
4Power connectionPanel earthing and rotation direction verifiedElectrician
5No-load runNo leaks, belts centred, no abnormal noiseMaintenance lead
6Emergency stop testEvery button stops the whole lineSafety officer
7First feedStable current and target fraction at low ratePlant operator
8Setting and handoverSettings and first sample recordedSite supervisor

The setting window of a worked example

Most layout decisions follow from the feed and discharge window of the unit itself. The figures below belong to the General 01 mobile crushing plant and are the ones used directly when planning stockpile count and truck cycles.

ParameterValue
Maximum feed size700 mm
Output size setting0-100 mm
Final product size0-5, 5-12, 12-19, 19-40 mm (standard, can be changed on request)
Capacity120-180 t/h
Optional generator550 kVA

What the first shift must record

Commissioning ends when the first shift log is closed, not when the plant starts turning. Crusher setting, screen apertures, feeder speed, measured product fractions and the reason for every stoppage go onto one sheet. That sheet is the only document that shortens the next set-up: on the following site the same material starts from the same setting instead of being rediscovered by trial and error.

Recurring commissioning mistakes

The most common is producing before levelling is finished; the second is opening the first feed at full rate; the third is letting the stockpile direction collide with the haul route, so the plant runs while haulage jams and rated capacity stays on paper. None of the three originates in the machine. All three are set-up decisions. The other field articles under jobsite and mobile plant follow the same logic into day-to-day operation.

Frequently asked questions: mobile crushing plant site commissioning plan

How many people does commissioning need

Headcount varies with the site. What matters is that each of the eight steps has a named owner; one person may own several steps, but no step may be ownerless.

Which material should the first feed use

The material the site will actually produce, fed thin. A trial run on a different feed does not carry its settings into real production.

Does the plan repeat when the unit relocates

Yes. Ground and layout steps are redone on every new site, while the setting steps get shorter whenever the previous site's log exists.

Definitions of technical terms: Glossary

Related Content

Export of Double Mobile Crushing Plant - Libya
PROCUREMENT AND SUPPLY

Export of Double Mobile Crushing Plant - Libya

We started to export General 02 and 03, our fully automatic Mobile Crushing Plants, which will be used in the reconstruction of the…

General 03 Planta Móvil de Trituración y Cribado de Piedra está en el  proceso de tranporte hacia la capital.
SHIPMENT & EXPORT

General 03 Planta Móvil de Trituración y Cribado de Piedra está en el proceso de tranporte hacia la capital.

The General 03 mobile crushing and screening plant, with 300 tonnes per hour capacity, is on its way to the Ankara site.

General 640 Mobile Stone Crushing Screening Plant in Medina
PRODUCT SHOWCASE

General 640 Mobile Stone Crushing Screening Plant in Medina

The General 640 mobile stone crushing and screening plant has arrived in Medina to begin work at the production site.

Mobile Stone Crushing Screening Plant continues work in snow-winter
PLANT EFFICIENCY

Mobile Stone Crushing Screening Plant continues work in snow-winter

A General 02 mobile plant keeps crushing through the Erzurum winter, because the site was prepared for cold conditions.