Skip to content

How to plan crushing plant lead time and shipment realistically

September 21, 2026
Crushing Plant Lead Time and Shipment Planning

Why lead time is never a single number

Procurement almost always opens with "how many weeks to delivery". In practice, crushing plant lead time is not a manufacturing calendar on its own. It is the sum of four blocks that queue behind each other: freezing the configuration, building and assembling, preparing the site on the buyer's end, and transport with customs clearance. The more of these run in parallel, the shorter the total; run in series, even excellent factory performance will not save the date.

The goal of planning is not a shorter date but a predictable one. A plant arriving two weeks late is usually manageable. Not knowing which week it arrives leaves every dependent item suspended, from the crusher foundation and the transformer connection to the crane hire.

The four blocks and what drives each

Blocks that make up the delivery calendar
BlockContentWhat drives the durationBuyer's responsibility
ConfigurationCapacity, number of stages, screen media, optionsHow many rounds technical approval takesSettle material analysis and product range
ManufacturingChassis, crusher, screen, conveyors, control panelStock position and special requestsReturn approved drawings without delay
Site preparationFoundations, power, access road, drainageConcrete curing and grid connection permitsFinish before the plant ships
Transport and customsLoading, routing, documentationOversize permits and border congestionCollect paperwork early

The third row is the one that decides most schedules. Site preparation sits entirely with the buyer, and when it slips the plant waits at the works instead of on site, which turns into storage and reloading cost.

Road gauge, the most underestimated constraint

Standard maximum road dimensions are largely harmonised across Turkey and the European Union. Once a load exceeds them, the movement becomes an abnormal transport with its own permit, routing, timing and escort conditions.

Standard maximum road dimensions
DimensionStandard limitNote
Width2.55 m2.60 m for refrigerated and insulated vehicles
Height4.00 mMeasured from the ground, load included
Articulated vehicle length16.50 mTractor and semi-trailer together
Road train length18.75 mTruck and drawbar trailer together

In Turkey, permits for loads beyond these limits are issued by the General Directorate of Highways; inside the European Union a separate permit is required from the road authority of every country on the route. Permits are written for a specific vehicle configuration, axle load diagram and approved itinerary. Bridge capacity, turning radii and overhead clearances are checked one by one during the route survey, and pilot vehicles or a police escort may be imposed depending on how far the load exceeds the limits.

Where a mobile plant has the advantage

A mobile crushing plant is designed with folding conveyors and a trailer-mounted chassis so that it can be brought close to standard dimensions on most routes. A stationary plant, by contrast, travels in pieces and is assembled on site, which is a deliberate trade between transport simplicity and erection time. The decision rests on the number of pieces, the mass of the heaviest single item and crane access at the destination.

Sea freight: choosing the loading method

For overseas shipment, cargo dimensions and mobility decide the loading method.

Sea freight options for heavy machinery
MethodSuitsGoverning constraint
Open top containerCargo too tall for the doors, crane loadedInternal length about 12.03 m, internal width about 2.35 m
Flat rackWide or heavy loads that may overhangNo side walls, overhang beyond the base is possible
RoRoWheeled or towable machineryRamp gradient and clear height
BreakbulkOversized items that cannot be containerisedCrane capacity and stowage plan

Container dimensions vary slightly by carrier and container age, so exact internal figures are confirmed with the line before booking. High cube open top variants offer more internal height than the standard type, and that difference occasionally decides whether a component has to be dismantled at all.

Documents, the item that quietly extends the calendar

Even a finished transport plan stalls at the port or the border when paperwork is incomplete. The headings to gather early are the commercial invoice and packing list, the certificate of origin, the declaration of conformity with the technical file, the insurance policy, the packaging declaration and, where required, an inspection report. Some import regimes ask for prior approval on specific items, and if those approvals do not run alongside manufacturing, the total calendar stretches. Comparable discipline on the spare parts side is collected under procurement and supply.

A buyer's checklist

Putting six facts in writing before contract removes most later disputes: delivery term and named place, mass and dimensions of the heaviest single piece, total number of pieces to be moved, width and gradient of the site access road, crane capacity needed for offloading, and how long the commissioning team stays on site. Once those six are settled, the delivery date stops being an estimate and becomes a planning input.

Common questions

What stretches lead time most?

Late technical approval and unfinished site preparation lead the list. Both can be closed before manufacturing even starts.

How long does an oversize permit take?

It depends on the country, the route and how far the load exceeds the limits, which is why the application should be tied to the day the route is fixed rather than to the loading date.

Should the plant ship whole or in pieces?

That follows from the heaviest piece, bridge limits along the route and crane access on site. Shipping whole shortens erection and increases the permit burden.

When must site preparation be finished?

Before the plant leaves the works, allowing for concrete curing. A load arriving at an unprepared foundation generates both storage and reloading cost.

Definitions of technical terms: Glossary

Related Content

Shipment to 3 Different Countries at the Same Time
PROCUREMENT AND SUPPLY

Shipment to 3 Different Countries at the Same Time

Heading into the 2026 summer season, our domestic and overseas crushing and screening plant shipments continue without slowing down…

100 - 150 Ton / Hour Capacity Stone Crushing and Screening Plant Shipment
SHIPMENT & EXPORT

100 - 150 Ton / Hour Capacity Stone Crushing and Screening Plant Shipment

Shipment of a stone crushing and screening plant with a capacity of 100 - 150 tonnes per hour, to be installed in Serbia, is comple…

Shipment of Our 500 Ton/Hour Capacity Crushing and Screening Plant Has Begun
SHIPMENT & EXPORT

Shipment of Our 500 Ton/Hour Capacity Crushing and Screening Plant Has Begun

The shipment of the 500 ton/hour capacity crushing and screening plant manufactured by General Makina has begun. Consisting of vari…

Leader manufacturer of Stone Crushing and Screening Plants
FAIRS & CONGRESSES

Leader manufacturer of Stone Crushing and Screening Plants

General Makina took part in the Antalya CM EXPO construction and construction equipment fair.