Sarajevo 2018: A Two-Stage Stationary Crushing Line with GPS120 + GTK650

Challenge
A fixed plant was needed in Sarajevo to crush run-of-mine material in two stages into cubical product for regional aggregate demand.
Solution
Fixed crushing and screening plant: GPS120 primary impact crusher in the first stage and GTK650 tertiary crusher in the final stage.
Result
The plant was completed in Sarajevo in 2018 and commissioned.
We completed the installation of this stationary crushing and screening plant in Sarajevo, the capital of Bosnia and Herzegovina, in 2018. The plant is built around a two-stage crushing layout.
The Line Has Two Stages
The first stage is handled by a GPS120 primary impact crusher, where run-of-mine material from the quarry is broken with a high reduction ratio. In the final stage, a GTK650 tertiary crusher shapes the product into the required sizes and a cubical form.
A Combination That Suits the Site
Bringing a primary impact crusher and a tertiary crusher together on one line makes it possible to combine high-capacity coarse crushing and quality aggregate production in a single plant. Delivered to the Sarajevo site, the plant was commissioned to meet the region's demand for aggregate.
If you are planning a similar stationary crushing and screening plant, tell us the material you will process and the capacity you are aiming for; our team will suggest a line layout suited to your project.
Sarajevo Stationary Plant – FAQ
Which crushers work in the plant?
A GPS120 primary impact crusher in the first stage and a GTK650 tertiary crusher in the final stage.
Where and when was the plant built?
In 2018, in Sarajevo, the capital of Bosnia and Herzegovina.
What does the plant produce?
Thanks to two-stage crushing, it turns run-of-mine material into cubical aggregate.
Could you build a similar plant for us?
Yes. Once you send us your material and capacity details, we prepare a quotation tailored to your project.